CONSTRUCTION COMMENCED

Pippis Construction

Stay up to date with the latest construction progress at Pippis as this exciting development takes shape.

From the early stages of construction through to the finishing touches, we’ll be sharing regular updates, project milestones and photos as work progresses.

Explore the latest construction updates below and follow the journey as Pippis comes to life.

October ’26 Construction Update

It’s a busy time at Pippis, with construction advancing strongly and the upper floors beginning to rise as the building takes shape.

The Hutchies tower crane was installed in mid-June which now stands prominently at a height of 40m over the site, forming a new landmark in the Coffs Harbour Jetty area.

Since then, rapid progress has been made, with daily deliveries of precast concrete façade panels, formwork, reinforcement steel and scaffolding to the site.

Over the coming weeks the building will rise through the upper floors, with the concrete structure scheduled to top out in January 2027.